NEWS RELEASE

PROVIDENCE ANNOUNCES MAJOR EXPANSION

Waco, Texas—The Providence Healthcare Network today announced plans for a major expansion to accommodate current and projected future growth in utilization. Included in the $48.5 million dollar project will be an expansion of the Emergency Department beds from 26 to 50, operating suites from 9 to 15, intensive care unit beds from 16 to 20, labor/delivery/recovery/post-partum (LDRP) beds from 9 to 11, and expansion of pulmonary and respiratory services, the radiology department, laboratory services, rehabilitation services, outpatient services, the medical record department, nutrition and dietary services, and classroom space. The additions will include a 10-bed acuity adaptable unit, 30-bed cardiac nursing unit, a 30-bed pre-operative/post-operative holding area, a surgery physicians’ lounge and changing area, an expanded congestive heart failure clinic, a relocated non-invasive cardiology services unit, a cardiopulmonary rehabilitation unit, and two shelled floors for future expansion.

The project will be financed entirely with hospital reserves and philanthropic gifts. The lead gift is from F.M. and Gloria Young. In recognition of their gift, the new 5-story addition at the front of the hospital will be named the F.M. and Gloria Davis Young Tower.

In making the announcement, Kent Keahey, President of the Providence Healthcare Network, noted that Providence has experienced significant growth over the years, and this growth has been accelerating in recent years. Continuation of this growth is expected with future population growth in the county and aging of the population.

The project is expected to commence in September and will take approximately 24 months to complete. Architects for the project are Joe Raso, Grant Dudley, and Bernadette Hookham of RBDR, PLLC. Construction manager for the project will be CMCT, Ltd., Mike Jackson, President, and John East, Vice President. Local contractors will be utilized to the maximum extent possible.

-END-

To view expansion photos, Click on each picture below

PROJECT FACT SHEET

New Facilities by Type:

5 Story Bed Tower (The Heart Hospital at Providence – F.M. & Gloria Young Tower) to Include:

  • New 30 Bed General Cardiac Nursing Unit
  • Increase in Intensive Care Unit Beds from 16 to 20
  • Addition of a new 10 bed Acuity Adaptable Unit
  • New Congestive Heart Failure Clinic
  • New Cardiac Rehab
  • New Classrooms for Education
  • 2 Shelled Floors for Future Expansion

First and Second Floor Expansion to Rear of Building to Include:

  • Increase in Emergency Department Rooms from 26 to 50
  • Expanded Radiology Services

Parking Garage

  • New 400 space parking garage

Expanded Services:

  • Increase in Labor/Delivery/Recovery/Post Partum (LDRP) Beds from 9 to 11
  • Increase in Operating Suites from 9 to 15
  • An Enlarged 30 Bed Pre-Operative/Post Operative Holding Area
  •  Pharmacy
  •  Food Services/Cafeteria
  • Medical Record Department
  • Respiratory Services

Recent Renovations Completed to Support Project:

  • New Peripheral Vascular Lab
  • Installation of Second CT Scanner
  • Expansion of Outpatient Procedure Unit
  • Expansion of Laboratory, Gastroenterology, Pulmonary Services, Physical Therapy and Joint Camp


Project Square Footage:
New Construction 161,920 sq. ft.
Renovation 66,939 sq. ft.
Parking Garage 120,000 sq. ft.

Project Cost:
Construction/Renovation $37,576,175
Furniture & Equipment $10,948,355
Total $48,524,530

Architect:
RBDR, PLLC Architects
913 Franklin Avenue, Suite 100
Waco, Texas 76701
254-776-8380 Office

Construction Manager:
CMCT, Ltd. (Centex Management Construction Technologies, Ltd.)
P. O. Box 506
Waco, Texas 76703-0506
254-399-8654

New Employees:
135 new employees on opening in 2007 increasing to a total of 242 by 2011. Total employment will increase from 1,910 full and part-time employees and 1,594 FTE’s as of June 2005 to approximately 2,071 full and part-time employees and 1,729 FTE’s in August 2007. By 2011, total employees will be approximately 2,200 full and part-time employees and 1,836 FTE’s.

Payroll Increase:
$6,650,000 on opening in 2007 increasing to $13,239,000 by 2011.

Dates:
Start September 2005; Completion August 2007

Phased Completion:
Parking Garage December 2006
The Heart Hospital at Providence January 2007
Emergency, Surgery, Radiology June 2007
Total Completion August 2007


 

   